“The cost of a new Duke Ellington School for the Arts has grown from $71 million to $178 million”

12694765895_a90fe8a561_z
Photo of 3500 R Street, NW by PoPville flickr user Jacques Arsenault

Office of the District of Columbia Auditor:

“The cost of a new Duke Ellington School for the Arts has grown from $71 million to $178 million without a comprehensive review by the D.C. Council on the location, other cost drivers, and all of the elements required for a performing arts high school, according to a new report by the D.C. Auditor.”

From ODCA’s executive summary (read the full report here):

“May 31, 2016

The Department of General Services Failed to Provide Information the DC Council Needed to Make Informed Decisions on the Scope and Cost of Modernizing the Duke Ellington School of the Arts
What ODCA Found:

 The Department of General Services (DGS) and The District of Columbia Public Schools (DCPS) failed to provide timely information to policy makers so they could make informed decisions on the location and desired level of investment for a new performing arts high school.

 DCPS did not finalize Educational Specifications for Duke Ellington School of the Arts before DGS proposed the project for inclusion in the FY 2012 District’s Capital Improvement Plan (CIP) adopted by the Council.

 DGS based initial and subsequent cost estimates for Duke Ellington on significantly different projects that did not take into account the costs required for a performing arts school.

 DCPS, DGS, and the Executive Office of the Mayor were not transparent while considering alternate sites for Duke Ellington—sites that might have cost less and/or better served the needs of the student population.

 DGS and D.C. Partners for the Revitalization of Education Projects, LLC (DC PEP) did not timely and accurately assess the need for and the cost of underground parking and other elements of the school at the Georgetown location.

 DGS and DC PEP did not provide updated cost information, milestone data and implementation timeframes in the CIP. DC PEP did not provide updated project costs and budgets to DGS and were not held accountable.

 The Project has seen significant delays as DGS and DC PEP have missed many of the benchmark dates laid out in the CIP and supporting documents. DGS and DC PEP underestimated the amount of time the design phase would take, causing a delay in schedule. Delays in meeting deadlines has contributed to the construction phase’s guaranteed maximum price still not being agreed upon.

 DGS has failed to require DC PEP to comply with its contractual obligations to the District government with regard to the Duke Ellington project. DGS failed to require its program manager to provide project management services consistent with the contract.

 DGS (and its predecessor, OPEFM) made decisions early on in the School Modernization Program that deprived the District of the use of competition as a tool to control costs.

 From its inception, the School Modernization Program has relied on a single program management firm, DC PEP, rather than multiple program management firms.

 The decision by DGS (and its predecessor, OPEFM) to use Design-Build procurement without competition on cost may have contributed to higher costs in the Duke Ellington School of the Arts modernization.

 The existing DGS Procedure and Delivery Manual is unclear and contradictory and does not provide guidance that promotes accountability. It has also not been followed consistently on the Duke Ellington Project.”

Recent Stories

Thanks to L. for sending this beautiful 98 Olds. Sweet City Ride is made possible by readers like you!

Ed. Note: If this was you, please email [email protected] so I can put you in touch with OP. “Dear PoPville, Where: Outside of Mi Vida on 14th St When: Tuesday…

“Eleanor II (all black) and Theo (tailless tuxie) newly of Van Ness. We lived in a basement unit before, so the cats are really loving the sunshine.” If you have…

photo by Diane Krauthamer “Dear PoPville, On Wednesday afternoon I fainted while riding my bike on 11th St NW, between NY Ave and Mass Ave (I think). I don’t remember…

Potomac Harmony is Back! Following a gap year of competing, then virtual rehearsals during the pandemic, followed by the well-earned retirement of our long-term director, a year of a director search, Potomac Harmony hit the regional contest stage in Concord, North Carolina in March for the first time since 2018! It was exhilarating, reaffirming, and rewarding!

The chorus hit all of its goals, the biggest of which was to have fun and sing our best on contest stage — we did both! Because we earned a score over 400 points, our new Director, Allison Lynskey, was awarded the Novice Director award, photo above. Additionally, one of our charter members, Jackie Bottash, was nominated for and honored with the Leadership Excellence award. It was a celebratory weekend!

What’s next? So much! We now look forward to upcoming performances, growing our membership, and expanding our musical product with new arrangements and an education component each week. It’s an exciting time to be part of this ever-growing ensemble!

Read More

Submit your own Announcement here.

Comedy Cabaret

Kick up your heels at Bad Medicine’s COMEDY CABARET extravaganza at the DC Improv Comedy Club on Tuesday, May 21st. Revel in the sights and sounds of this entertaining musical revue, with songs, dance and sketch comedy that will have

×

Subscribe to our mailing list