“First Street NW is anticipated to open in mid-October 2016 and V Street NW by the end of October 2016”

by Prince Of Petworth August 31, 2016 at 3:40 pm 15 Comments

fst-summary-large-e1450888130853

Thanks to a couple of readers for passing on the First Street Tunnel Community Update from DC Water:

“DC Water is diligently working towards making the First Street Tunnel operational by late September 2016. Construction is behind schedule due to the excavation of the frozen ground taking longer than anticipated and delays in the delivery of some key custom fabricated equipment. Major remaining work includes the testing of the system, demolition of temporary works and street restoration. We apologize for the delay and appreciate your patience as we move to project completion.

Updates at Construction Staging Areas (CSAs)

Channing Street CSA: Finalizing construction of the shaft cover and ventilation control vault, backfilling and landscaping.

Adams Street CSA: Installing surface access on the shaft cover, demolition of temporary works, backfilling and site restoration is ongoing. Adams Street NW and Flagler Place NW are expected to reopen at the end of October 2016. The CSA on Flagler Place has been reduced, the street partially repaved and most of the sidewalk restored.

V Street CSA: Finalizing construction of the shaft cover, demolition of temporary works, utility relocations, backfilling and site restoration is ongoing. First Street NW is anticipated to open in mid-October 2016 and V Street NW by the end of October 2016.

Pumping Station CSA: Testing of the Pumping Station is underway, construction of permanent power, utility connections and site restoration ongoing. Thomas Street NW is anticipated to reopen at the end of September 2016.”

×