This Weekend’s Metro Track Work

by Prince Of Petworth June 6, 2014 at 3:55 pm 0

dc_metro_track_work
Photo by PoPville flickr user jiconoclast

From WMATA:

Red Line
Trains every 10-20 minutes

Red Line trains will operate as follows from 10 p.m. Friday through closing Sunday:

Between Shady Grove & Glenmont: Every 20 minutes throughout the weekend
Between Grosvenor & NoMa-Gallaudet: Every 10 minutes from 9AM-9PM on Saturday and 9AM-10PM on Sunday

Work Performed: Insulator and fastener renewal, and fence and light pole replacement between NoMa-Gallaudet and Rhode Island Avenue; switch replacement at Shady Grove.

Orange Line
Trains every 24 minutes

Orange Line trains will operate every 24 minutes throughout the weekend.

Work Performed: Improvements to track infrastructure including rail tie, fastener, and insulator renewal between East Falls Church and West Falls Church; platform reconstruction between Stadium-Armory and Cheverly.

Blue Line
Trains every 20 minutes

Blue Line trains will operate every 20 minutes throughout the weekend.

Work Performed: Improvements to infrastructure including grout pad replacement, rail fastener renewal, communications upgrades and switch installation between Pentagon City and Ronald Reagan Washington National Airport.

Yellow Line
Trains every 20 minutes

Yellow Line trains will operate as follows from 10 p.m. Friday through closing Sunday:

On Saturday, between Huntington and Mt. Vernon Sq every 20 minutes
On Sunday, between Huntington and College Park every 20 minutes

Work Performed: Improvements to infrastructure including grout pad replacement, rail fastener renewal, communications upgrades and switch installation between Pentagon City and Ronald Reagan Washington National Airport.

Green Line
Regular service EXCEPT Saturday during daytime hours at Greenbelt Station only

On Saturday, Green Line trains will operate:

Between College Park & Branch Ave at regular weekend intervals (every 12 minutes 9AM-9PM)
At Greenbelt Station only, trains will arrive and depart every 24 minutes between 9AM-9PM

Regular weekend service on Sunday.

Work Performed: Ongoing construction of new 7000-series test track”

×