49°Partly Cloudy

“Metro to restore normal service at Stadium-Armory in about three months, less than initial estimates”

by Prince Of Petworth October 21, 2015 at 3:10 pm 3 Comments

From WMATA:

“Metro has published a project webpage to keep customers and the community informed about the effort to rebuild the Traction Power Substation outside Stadium-Armory that was heavily damaged in a fire on September 21.

Following a full week of equipment testing, the project remains on track for completion this calendar year — about three months sooner than originally projected. Metro will restore normal service on the Blue, Orange and Silver lines as soon as the substation is returned to service.

Riders can view a video [above] and get details about upcoming project milestones by visiting here.

×

Subscribe to our mailing list